Haslam Water Supply Main Replacement

Powell River, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.8M
$1,764,401
Federal share50%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Powell River
Construction start
Sep 11, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 10, 2017
  • Construction end5 weeks earlyforecast Mar 31, 2020