Consolidated Wastewater Treatment

Powell River, British Columbia

completeWastewaterGIS
Federal contribution
$30.4M
$30,400,000
Federal share40%

of $76.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
2020202120222023
Built

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Powell River
Construction start
Oct 13, 2020(actual)
Construction end
Aug 8, 2023(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Nov 30, 2020
  • Construction end7 weeks lateforecast Jun 23, 2023