North Lagoon Trunkmain

Fort St. John, British Columbia

completeWastewaterISF
Federal contribution
$1.4M
$1,426,928
Federal share33%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Fort St. John
Construction start
Apr 1, 2010(actual)
Construction end
Oct 31, 2011(actual)