Back to projects

96th Avenue Widening and Intersection Improvements

Langley, British Columbia

completeHighways and RoadsISF
Federal contribution
$787,880
Federal share24%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Langley
Construction start
Aug 24, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 19, 2010
  • Construction end3 months lateforecast Jul 26, 2011

Also in Langley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36773 in the federal list. How to read these figures.