96th Avenue Widening and Intersection Improvements
Federal contribution
$787,880
Federal share24%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Langley
- Construction start
- Aug 24, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 19, 2010
- Construction end3 months lateforecast Jul 26, 2011
Also in Langley