100th Avenue Expansion

Fort St. John, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,398,595
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Fort St. John
Construction start
Apr 26, 2010(actual)
Construction end
Mar 31, 2011(actual)

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36785 in the federal list. How to read these figures.