South East Balancing Reservoir

Merritt, British Columbia

completeDrinking WaterISF
Federal contribution
$535,116
Federal share23%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Merritt
Construction start
Sep 15, 2010(actual)
Construction end
Mar 30, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Dec 15, 2010