South East Balancing Reservoir
Federal contribution
$535,116
Federal share23%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Merritt
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Mar 30, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Dec 15, 2010
Also in Merritt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36832 in the federal list. How to read these figures.