Waste Water Capacity Improvements

Cranbrook, British Columbia

completeWastewaterISF
Federal contribution
$4.8M
$4,815,000
Federal share33%

of $14.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Cranbrook
Construction start
Jul 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 14, 2010