Back to projects

City of Cranbrook Phillips UV Disinfection Facility

Cranbrook, British Columbia

underwayDrinking WaterGIS
Federal contribution
$5.2M
$5,195,916
Federal share40%

of $13.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2024
today
20242025202620272028
BuiltForecast

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Cranbrook
Construction start
May 1, 2026(actual)
Construction end
Dec 1, 2027(forecast)

Also in Cranbrook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66914 in the federal list. How to read these figures.