completeVentilationCVRIS
Federal contribution
$2.6M
$2,577,630
Federal share100%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 23, 2021(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Nov 2, 2021
  • Construction end2 months earlyforecast Jun 15, 2025