Cranbrook City Hall - Renovations and Upgrades

Cranbrook, British Columbia

completeVentilationCVRIS
Federal contribution
$1.2M
$1,209,373
Federal share80%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Cranbrook
Construction start
May 2, 2022(actual)
Construction end
Jul 28, 2023(actual)

Against the original forecast

  • Construction end5 months earlyforecast Dec 31, 2023

Also in Cranbrook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60397 in the federal list. How to read these figures.