Highway 104 - Pine Tree Road Overpass
Federal contribution
$1.1M
$1,125,000
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Oct 8, 2010(actual)
- Construction end
- Sep 20, 2011(actual)
Against the original forecast
- Construction end3 weeks lateforecast Aug 31, 2011
Also in Pictou