Wastewater Management Upgrades
Federal contribution
$33,715
Federal share33%
of $102.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 23, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Annapolis
- Construction start
- Feb 22, 2010(actual)
- Construction end
- Mar 18, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jan 15, 2010
- Construction end3 months lateforecast Dec 31, 2010
Also in Annapolis Royal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36964 in the federal list. How to read these figures.