Back to projects

Upgrades to Cunningham-Babcock Forest Service Road

Quesnel, British Columbia

completeHighways and RoadsISF
Federal contribution
$260,000
Federal share47%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 15, 2010(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2010
  • Construction end4 weeks earlyforecast Nov 30, 2010

Also in Quesnel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37271 in the federal list. How to read these figures.