Bridge Replacement on Nahmint 3 Forest Service Road

Port Alberni, British Columbia

completeHighways and RoadsISF
Federal contribution
$124,726
Federal share48%

of $259.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 19, 2010(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2010
  • Construction end4 weeks earlyforecast Nov 30, 2010

Also in Port Alberni

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37282 in the federal list. How to read these figures.