Bridge Replacement on Nahmint 3 Forest Service Road
Port Alberni, British Columbia
Federal contribution
$124,726
Federal share48%
of $259.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Aug 19, 2010(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2010
- Construction end4 weeks earlyforecast Nov 30, 2010
Also in Port Alberni
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37282 in the federal list. How to read these figures.