Widening of Spius Creek Forest Service Road

Merritt, British Columbia

completeHighways and RoadsISF
Federal contribution
$40,103
Federal share46%

of $87.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 21, 2010(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Nov 30, 2010