Resurfacing Highway 10
Federal contribution
$305,050
Federal share28%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 30, 2010
- Construction end2 weeks lateforecast May 31, 2011
Also in Langley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37360 in the federal list. How to read these figures.