Back to projects

Upgrades to the First Peoples Gallery of the Royal British Columbia Museum

Victoria, British Columbia

completeCultureISF
Federal contribution
$1.3M
$1,344,214
Federal share50%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Also in Victoria