208 Street - Road and Utility Renewal
Federal contribution
$1.7M
$1,679,681
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 16, 2009
ApprovedJan 25, 2010
2010
Built
Approved 3 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Langley
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Oct 22, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 1, 2009
- Construction end5 weeks lateforecast Sep 15, 2010