Ogden Point Deep Sea Terminal Pier Expansion

Victoria, British Columbia

completeMarineISF
Federal contribution
$764,684
Federal share28%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 19, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Feb 2, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Oct 1, 2009

Also in Victoria

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39142 in the federal list. How to read these figures.