108 Mile Water Reservoir Replacement
Federal contribution
$235,156
Federal share21%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of Cariboo
- Construction start
- Jun 15, 2010(actual)
- Construction end
- Feb 10, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 15, 2010
- Construction end2 months lateforecast Nov 30, 2010
Also in Cariboo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39152 in the federal list. How to read these figures.