108 Mile Ranch Water System
Federal contribution
$981,118
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2015
2016201720182019
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Regional District of Cariboo
- Construction start
- May 1, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction end4 months lateforecast Nov 30, 2018
Also in Cariboo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46140 in the federal list. How to read these figures.