BC Hydro Customer Connection Project: Barkerville Gold Mines Electrification
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2023
202320242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- British Columbia Hydro and Power Authority
- Construction start
- May 13, 2024(actual)
- Construction end
- Dec 4, 2024(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 13, 2024