Village of McBride Wastewater Lagoon Cell 1 Revitalization

Cariboo, British Columbia

completeWastewaterGIS
Federal contribution
$391,958
Federal share40%

of $979.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2023
202320242025
Built

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of McBride
Construction start
Jun 29, 2023(actual)
Construction end
Nov 30, 2024(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jul 17, 2023
  • Construction end4 weeks earlyforecast Dec 31, 2024