Sewage Lagoon

Mackenzie, British Columbia

completeWastewaterISF
Federal contribution
$342,470
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Mackenzie
Construction start
Aug 3, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011