Mackenzie Recreation Centre - Energy Recovery and Facility Upgrades
Federal contribution
$2.4M
$2,395,753
Federal share70%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 12, 2023
202320242025
Built
Approved 7 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- District of Mackenzie
- Construction start
- Jun 27, 2023(actual)
- Construction end
- Dec 24, 2024(actual)
Against the original forecast
- Construction start14 months lateforecast May 1, 2022
- Construction end4 months lateforecast Aug 28, 2024