Parsnip River Bridge Replacement
Federal contribution
$12.9M
$12,903,246
Federal share50%
of $25.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 27, 2016
201720182019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- Mar 15, 2018(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jan 31, 2018
- Construction end4.7 years earlyforecast Sep 30, 2026
Also in Mackenzie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45842 in the federal list. How to read these figures.