Parsnip River Bridge Replacement

Mackenzie, British Columbia

completeHighways and RoadsNRP
Federal contribution
$12.9M
$12,903,246
Federal share50%

of $25.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 27, 2016
201720182019202020212022
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Mar 15, 2018(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jan 31, 2018
  • Construction end4.7 years earlyforecast Sep 30, 2026

Also in Mackenzie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45842 in the federal list. How to read these figures.