District of Mackenzie Community Water Supply Well

Mackenzie, British Columbia

completeDrinking WaterCWWF
Federal contribution
$352,030
Federal share50%

of $704.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Mackenzie
Construction start
Jan 15, 2018(actual)
Construction end
Oct 12, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 27, 2018
  • Construction end2 months lateforecast Aug 10, 2018