Vancouver Landfill - Water Line Extension
Federal contribution
$311,452
Federal share31%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Dec 20, 2010(actual)
- Construction end
- Jul 18, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Dec 6, 2010
- Construction end3 weeks lateforecast Jun 30, 2011
Also in Delta
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39371 in the federal list. How to read these figures.