Highway 17 - 28th Avenue Overpass

Delta, British Columbia

completeHighways and RoadsISF
Federal contribution
$2.4M
$2,387,500
Federal share50%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 4, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 30, 2010
  • Construction end4 weeks earlyforecast Aug 31, 2011

Also in Delta