Back to projects

Surface Repairs on Highway 20 in Le Bic

Rimouski, Quebec

completeHighways and RoadsISF
Federal contribution
$500,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 7, 2010(actual)
Construction end
Jun 22, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 30, 2010
  • Construction end4 months earlyforecast Oct 30, 2010

Also in Rimouski

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39646 in the federal list. How to read these figures.