Sandbanks Provincial Park Picnic Shelter
Federal contribution
$46,479
Federal share46%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Oct 12, 2010(actual)
- Construction end
- Mar 4, 2011(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 10, 2010
Also in Picton