Annacis Island Parkway Pavement Renewal
Federal contribution
$347,175
Federal share47%
of $734.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2010
Built
Approved 5 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Apr 19, 2010(actual)
- Construction end
- Jun 24, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 1, 2010
- Construction end5 weeks earlyforecast Jul 31, 2010
Also in Delta
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40277 in the federal list. How to read these figures.