Back to projects

Rehabilitation of Highway 564

Rocky View County, Alberta

completeHighways and RoadsISF
Federal contribution
$830,500
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Sep 30, 2010(actual)
Construction end
Oct 21, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Rocky View County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40474 in the federal list. How to read these figures.