Highway 1 Median Cable Barrier
Federal contribution
$245,685
Federal share27%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 19, 2010
ApprovedSep 8, 2010
2011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Nov 9, 2010(actual)
- Construction end
- Feb 21, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2010
- Construction end2 months lateforecast Dec 21, 2010
Also in Chilliwack
- Vedder Bridge Replacement$4.2M
- Chilliwack - Design and Construction of Organic Food Waste Receiving and Pre-Processing Station & Digester # 4$3.6M
- City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2$3.6M
- Replacement of Sanitary Sewers$1.3M
- Chilliwack - Evans Road Connector$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41234 in the federal list. How to read these figures.