Carling Heights - Facility Expansion
Federal contribution
$120,000
Federal share33%
of $360.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
Built
Approved 5 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Jan 31, 2011(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41538 in the federal list. How to read these figures.