Water Transmission Main Installation - Bakery Lane

East Hants, Nova Scotia

completeDrinking WaterISF
Federal contribution
$180,000
Federal share33%

of $540.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of East Hants
Construction start
Dec 1, 2010(actual)
Construction end
Mar 29, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Nov 15, 2010