Chilliwack - Collinson Pump Station Upgrade

Chilliwack, British Columbia

completeDisaster MitigationCC
Federal contribution
$833,333
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2014
20152016
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Chilliwack
Construction start
Jul 1, 2014(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Feb 28, 2016

Also in Chilliwack

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44861 in the federal list. How to read these figures.