Boundary Bay Dike Foreshore Protection (2 Sites)

Delta, British Columbia

completeDisaster MitigationCC
Federal contribution
$252,555
Federal share25%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2014
20152016
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Sep 15, 2014(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Feb 28, 2016

Also in Delta

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44864 in the federal list. How to read these figures.