Rehabilitation of Letendre Street

Asbestos, Quebec

completeWastewaterCC
Federal contribution
$177,812
Federal share33%

of $533.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Asbestos
Construction start
Mar 16, 2015(actual)
Construction end
Nov 3, 2016(actual)

Against the original forecast

  • Construction start2 months earlyforecast May 18, 2015
  • Construction end10 months lateforecast Dec 31, 2015

Also in Asbestos

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45905 in the federal list. How to read these figures.