Renewal of water pipes
Federal contribution
$337,483
Federal share50%
of $675.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2017
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Asbestos
- Construction start
- Oct 14, 2016(actual)
- Construction end
- Dec 14, 2016(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 7, 2016
- Construction end16 months earlyforecast Mar 31, 2018