Back to projects

Water Systems Upgrade

Asbestos, Quebec

completeWastewaterGIS
Federal contribution
$1.8M
$1,756,945
Federal share40%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Asbestos
Construction start
Jun 30, 2020(actual)
Construction end
Aug 22, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2020
  • Construction end2 weeks earlyforecast Sep 5, 2022

Also in Asbestos