Back to projects

Wastewater Retention Pond

Asbestos, Quebec

completeWastewaterCWWF
Federal contribution
$306,659
Federal share50%

of $613.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 26, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Asbestos
Construction start
May 8, 2017(actual)
Construction end
Nov 24, 2018(actual)

Also in Asbestos

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48925 in the federal list. How to read these figures.