Wastewater Retention Pond
Federal contribution
$306,659
Federal share50%
of $613.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Asbestos
- Construction start
- May 8, 2017(actual)
- Construction end
- Nov 24, 2018(actual)
Also in Asbestos