Infrastructure repairs in various sectors of the City of Boucherville.
Federal contribution
$2.1M
$2,128,300
Federal share33%
of $6.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201320142015201620172018
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Boucherville
- Construction start
- Oct 16, 2012(actual)
- Construction end
- Jan 3, 2018(actual)
Against the original forecast
- Construction start2.6 years earlyforecast May 25, 2015
- Construction end2 years lateforecast Dec 31, 2015