Water System Upgrades
Federal contribution
$166,250
Federal share40%
of $415.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Boucherville
- Construction start
- Aug 26, 2020(actual)
- Construction end
- Nov 10, 2020(actual)
Also in Boucherville
- Infrastructure repairs in various sectors of the City of Boucherville.$2.1M
- Program for the renewal of drinking water and wastewater pipes$1.8M
- Development of the Mortagne Park-and-Ride Facility$1.0M
- Replacement and upgrade of cooling systems$286.5K
- Program for the renewal of drinking water and wastewater pipes$106.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56466 in the federal list. How to read these figures.