Back to projects

Replacement and upgrade of cooling systems

Boucherville, Quebec

completeVentilationCVRIS
Federal contribution
$286,470
Federal share80%

of $358.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 31, 2021(actual)
Construction end
Feb 24, 2023(actual)

Against the original forecast

  • Construction end18 months lateforecast Aug 31, 2021

Also in Boucherville