Development of the Mortagne Park-and-Ride Facility
Federal contribution
$1.0M
$1,027,899
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018201920202021
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- May 1, 2019(actual)
- Construction end
- Jan 15, 2021(actual)
Also in Boucherville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51127 in the federal list. How to read these figures.