Renovation of Belle-Vue community centre and redevelopment of Saint-Félicien municipal wharf

Saint-Félicien, Quebec

completeRecreationCC
Federal contribution
$88,334
Federal share33%

of $265.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Saint-Félicien
Construction start
Sep 1, 2015(actual)
Construction end
Dec 31, 2015(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2015