Ventilation and Air Conditioning System Rehabilitation in Bloc D
Federal contribution
$386,100
Federal share58%
of $670.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de St-Félicien
- Construction start
- May 3, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2021
Also in Saint-Félicien