Back to projects

Water Systems Upgrades

Saint-Félicien, Quebec

completeWastewaterGIS
Federal contribution
$137,550
Federal share40%

of $343.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Saint-Félicien
Construction start
May 16, 2022(actual)
Construction end
Dec 30, 2022(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2022
  • Construction end15 months earlyforecast Mar 31, 2024

Also in Saint-Félicien

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56734 in the federal list. How to read these figures.