Water Systems Upgrades
Federal contribution
$137,550
Federal share40%
of $343.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 18, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Saint-Félicien
- Construction start
- May 16, 2022(actual)
- Construction end
- Dec 30, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2022
- Construction end15 months earlyforecast Mar 31, 2024
Also in Saint-Félicien
- Saint-Félicien Marina and Municipal Wharf$1.5M
- Program for the renewal of drinking water and wastewater pipes$958.7K
- Water Systems Upgrades$734.2K
- Ventilation and Air Conditioning System Rehabilitation in Bloc D$386.1K
- Renovation of Belle-Vue community centre and redevelopment of Saint-Félicien municipal wharf$88.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56734 in the federal list. How to read these figures.