Schedule

Announced and approvedSep 18, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Saint-Félicien
Construction start
Jun 21, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Dec 17, 2021